DeliveryMetrics
MetricsIllustrative · demo data
Portfolio analytics - cost and schedule performance, forecast uncertainty, risk cover, and the exception triggers each project has tripped.
Real project names, invented forecasts - not actual NZTA figures.
Portfolio CPI
1.00
cost performance, from summed earned value
Portfolio SPI
0.98
schedule performance, from summed earned value
Exception triggers
5
tripped across 3 of 6 projects
Within risk cover
3 of 6
exposure at or below contingency
Cost and schedule performance
Each project's SPI against its CPI. Below either 0.90 line is an exception.
0.800.800.900.901.001.001.101.10Ahead and under costBehind and over costSPI (schedule performance)CPI (cost performance)Central Plains Water Scheme: SPI 0.98, CPI 0.99 (Early / provisional)Central PlainsTe Pae Christchurch Convention Centre: SPI 0.86, CPI 0.88 (At risk)Te PaeChristchurch International Airport Works Programme: SPI 0.93, CPI 0.96 (Watch)AirportUC Rutherford Regional Science and Innovation Centre: SPI 1.02, CPI 1.01 (On track)UC RutherfordAuckland City Rail Link: SPI 1.00, CPI 1.01 (On track)City Rail LinkNew Dunedin Hospital: SPI 0.91, CPI 0.93 (Watch)Dunedin Hospital
Early / provisionalAt riskWatchOn trackDashed lines: 0.90 exception trigger
Risk cover
Live risk exposure as a multiple of the contingency left to absorb it.
Te Pae
7.0x · $21M / $3M
Dunedin Hospital
3.4x · $95M / $28M
Airport
1.6x · $14M / $9M
Central Plains
0.9x · $30M / $34M
City Rail Link
0.4x · $24M / $55M
UC Rutherford
0.4x · $5M / $12M
The vertical rule is 1x, where live risk equals the contingency left to absorb it.
Forecast uncertainty
The P10 to P90 finish range against each project's baseline duration. The tick is the P50 most likely finish; a wide range means the forecast is still provisional.
Te Pae
P50 +9 mo · range 10 mo
Dunedin Hospital
P50 +12 mo · range 22 mo
Airport
P50 +4 mo · range 8 mo
Central Plains
P50 +3 mo · range 14 mo
UC Rutherford
P50 +0 mo · range 5 mo
City Rail Link
P50 -2 mo · range 6 mo
-10%baseline+10%+20%+30%+40%
Exception triggers
Thresholds that demand attention whatever the written status says: CPI below 0.90, SPI below 0.90, Risk exposure above contingency. From the Early Warning and Project Controls references.
ProjectStatusCPISPIExposure / contingencyTriggers
Te Pae Christchurch Convention CentreAt risk0.880.86$21M / $3M3 of 3
New Dunedin HospitalWatch0.930.91$95M / $28M1 of 3
Christchurch International Airport Works ProgrammeWatch0.960.93$14M / $9M1 of 3
Central Plains Water SchemeEarly / provisional0.990.98$30M / $34M0 of 3
Auckland City Rail LinkOn track1.011.00$24M / $55M0 of 3
UC Rutherford Regional Science and Innovation CentreOn track1.011.02$5M / $12M0 of 3