At 97% complete the project is through construction and into the low-risk tail: CPI 1.01 and SPI 1.00 sit on plan, and remaining contingency ($55M) comfortably covers live risk exposure ($24M). The historical overrun is already absorbed into the current baseline, so what remains is a systems-integration and handover story, not a cost story. Narrative and numbers agree; confidence is high.
Generated from the project's earned-value position, contingency and risk register. The forecast is statistical; the AI explains it and flags where the narrative and the numbers disagree. Ask the assistant for the detail behind any figure.